Waterproofing defects that NSW auditors often find in apartment buildings are not exotic. They are commonly; missed puddle flanges, flat balconies, membranes stopped short at sliding doors and bond breakers that are too narrow.
This guide sets out the ten waterproofing defects Building Commission NSW lists in its Building Defects Library, the NCC and Australian Standard clauses behind each one, and a stage-by-stage inspection routine for catching them before the membrane is covered and well before handover.
Waterproofing defects NSW: why they still top the list
The 2025 Strata Defects Research from Building Commission NSW found that 53% of buildings in the survey had serious defects, about the same as in the 2023 research. Waterproofing was the most common serious defect at 22%, ahead of fire safety systems at 16%.
Both rates fell in 2025, and buildings registered in 2022–2024 had lower serious-defect rates than those registered in 2018–2021. The survey covered strata managers of Class 2 schemes of four storeys and above registered between July 2018 and June 2024.
Waterproofing keeps failing because the membrane ends up buried under screeds, tiles and pavers. A wrong fall is cheap to fix while exposed and expensive once the unit is occupied.
What’s at stake for builders under NSW law
According to the Building Defects Library, the regulator (then part of Fair Trading) began proactive audits of Class 2, 3 and 9c buildings in September 2020. Building Commission NSW itself launched on 1 December 2023. In NSW, the Residential Apartment Buildings (Compliance and Enforcement Powers) Act 2020 (the RAB Act) lets the Commission stop work to deal with serious defects, require developers to fix non-compliant work and impose penalties, with a focus on stepping in before an occupation certificate is issued. The Design and Building Practitioners Act 2020 (the DBP Act) added a statutory duty of care, registration for most practitioners on Class 2 buildings and compliance declarations.
The Commission’s summary of the RAB Act definition includes failures to meet Building Code of Australia performance requirements, Australian Standards or approved plans, and defects related to a building element. Waterproofing is one of the five building elements, and the Commission lists bathrooms, balconies, roofs and planter boxes as examples of where serious waterproofing defects occur. Wet-area waterproofing inside an apartment is generally common property unless the area has been renovated.
Registrations for Project Intervene have closed, but an owners corporation can still lodge a complaint with the Commission, and that can end in a developer undertaking or a building work rectification order.
The 10 waterproofing defects in the Building Defects Library
The library (v1.1, June 2025) is written for certifiers, councils and industry. It lists defects that recur in Commission audits, can be recognised without specialist testing, and cost far more to fix after occupation. That makes them ideal hold points.
| No. | Defect | Where | Main reference |
|---|---|---|---|
| 2.1 | Membrane not terminated into the puddle flange at a drain | Roof or balcony | AS 4654.2 cl 2.10 |
| 2.2 | Membrane not turned into an overflow | Roof or balcony | AS 4654.2 cl 2.11 |
| 2.3 | Retained water, ponding or inadequate falls | Roof or balcony | AS 4654.2 cl 2.5.2 |
| 2.4 | Inadequate surface preparation | External surface or roof | AS 4654.2 cl 2.5 |
| 2.5 | Inadequate membrane termination at a sliding door | Balcony door | AS 4654.2 cl 2.8 |
| 2.6 | Ponding or inadequate falls in the general area | Bathroom | NCC F2D4 |
| 2.7 | Ponding or inadequate falls in the shower | Shower | AS 3740 cl 2.3.2 |
| 2.8 | No waterstop angle at the doorway | Wet area | AS 3740 cl 4.9.1 |
| 2.9 | Internal puddle flange not recessed into the substrate | Wet area | AS 3740 cl 4.3.1 |
| 2.10 | Incorrect fillet size at the wall-to-floor junction | Wet area | AS 3740 cl 4.10 |
Balconies, roofs and podiums (AS 4654.2)
- Drains (2.1): the membrane must be turned down into the drain inlet, or clamped or attached to a flange. With a liquid membrane, it is applied onto the puddle flange and carried down.
- Overflows (2.2): the membrane is turned into the overflow so moisture can’t track behind it. It doesn’t need to be if the pre-formed outlet has a flange.
- Falls (2.3): water must not sit on the finished surface, apart from residue held by surface tension. The fall goes in the structural substrate or a screed, and should be no flatter than 1 in 100.
- Substrate (2.4): for fully bonded or liquid-applied membranes, the substrate must be smooth, clean, dry and free of dust, with no protrusions, voids or formwork distortions, and its moisture content must suit the membrane.
- Sliding doors (2.5): sub-sill flashing must be part of the membrane system, and the upturn must stop water, including wind-driven rain, getting over the top. The standard doesn’t set a mandatory upturn height (it points to an informative appendix), and the library says the façade engineer should decide it.
Bathrooms, showers and laundries (AS 3740)
- General floor falls (2.6): under NCC 2022 F2D4, a Class 2 or 3 bathroom or laundry above a sole-occupancy unit or public space needs a floor waste, with continuous falls of at least 1:80 and no steeper than 1:50.
- Shower falls (2.7): AS 3740-2021 requires at least 1:80 to the waste in the shower area.
- Waterstops (2.8): the waterstop’s vertical leg finishes flush with the finished floor. Perimeter flashing needs a vertical leg at least 25 mm above finished floor level (except across doorways) and a horizontal leg at least 50 mm wide.
- Leak control flanges (2.9): recessed into the substrate, not sitting above it, sealed to the riser and fixed so they can’t move.
- Fillets and bond breakers (2.10): needed at every change of plane or material and at movement joints where the membrane is bonded to the substrate. Minimum bond breaker widths are 100 mm for Class 1 membranes, 35 mm for Class 2 and 12 mm for Class 3.
Which standards apply: AS 3740, AS 4654.2 and the NCC
As the library sets out, NCC 2022 F1D5 requires roofs, balconies, podiums and similar horizontal surfaces to have a membrane made of materials that comply with AS 4654.1, designed and installed to AS 4654.2. F2D2 requires wet areas in Class 2 and 3 buildings to comply with AS 3740 and Specification 26.
Watch the falls conflict. AS 3740-2021 allows a 1:100 minimum in general wet areas, but NCC 2022 sets 1:80. The library notes that where the standard contradicts the NCC, the NCC prevails. The library is based on NCC 2022, so confirm with the principal certifier which edition applies to your building. Keep the waterproofing design, specification and manufacturer’s data sheets on site for details the standards leave open.
A stage-by-stage waterproofing inspection routine
Inspect at a hold point before each layer is covered, photograph every detail against its location, and don’t release the next trade until the item is closed. Take extra care with terminations on exposed upper storeys and coastal sites.
Stage 1: Substrate and falls, before the membrane
- Check falls with a level or digital inclinometer and photograph the reading next to the drain or waste (2.3, 2.6, 2.7).
- Check the substrate is smooth, clean and dry, with no protrusions or voids (2.4).
- Confirm drain, overflow and floor-waste positions match the drawings.
Stage 2: Drainage connections and junction details
- Leak control flanges recessed and sealed. External drain connections and overflows detailed so the membrane can be turned in (2.1, 2.2, 2.9).
- Fillets and bond breakers at every change of plane, sized for the membrane class being used (2.10).
- Waterstop angles at wet-area doorways and sub-sill flashings at sliding doors in place before the membrane goes on (2.5, 2.8).
Stage 3: Cured membrane and terminations
- Coverage is continuous, upturns and perimeter flashings reach the required heights, and laps and penetrations are sealed. Record the product used.
- As good practice, run a flood or ponding test in line with the project specification and the manufacturer’s instructions. Photograph the start and finish and record the result.
- Protect the membrane from following trades and log any damage straight away.
Stage 4: Finishes and the pre-handover walk
- Water test the finished floors: no ponding beyond surface-tension residue, and falls run to the wastes and drains.
- Check variable-height drain grates, sliding door sills and thresholds are at the finished levels.
- Before practical completion, walk every wet area and balcony against all ten library defects and close open items with “after” photos.
How to record waterproofing defects so they actually get fixed
A waterproofer can’t fix “bathroom leaking”. Each record should include the unit and room, an annotated photo, the measured value (such as a 1:110 fall reading), the library defect number and clause, the responsible trade and a due date. Quoting library references keeps everyone working from the same clause. Ask for a close-out photo from the same angle before closing an item, and keep the records through the defects liability period in case the owners corporation raises a query later. Our guide to effective building defect reporting covers the basics in more detail.
Using DefectWise inspection software, you can set up the ten library defects as categories, capture and annotate photos on site even without coverage, assign each item to the waterproofer through the contractor portal, and produce the inspection report as a PDF when you’re finished.
Put the routine into practice
The regulator has said where it keeps finding problems, so build your hold points around those ten defects. For the wider compliance picture, see our overview of construction regulations and compliance in Australia and New Zealand and how defect management improves construction quality.
Ready to run your next waterproofing inspection digitally? Create a free DefectWise account and set up your first project in minutes.
Frequently asked questions about waterproofing defects in NSW
Waterproofing. In the 2025 Building Commission NSW research, waterproofing defects were the most prevalent serious defect at 22%, ahead of fire safety systems at 16%.
AS 3740-2021 requires at least 1:80 in the shower area. For Class 2 and 3 buildings, NCC 2022 F2D4 requires falls between 1:80 and 1:50 to the floor waste, as summarised in the Building Defects Library.
AS 4654.2 covers design and installation, and materials must comply with AS 4654.1. NCC 2022 F1D5 calls up both.
Yes. Waterproofing is one of the five building elements, and the RAB Act definition of a serious defect covers defects related to a building element, so waterproofing failures can lead to regulator action.
Building Commission NSW publishes it as a PDF (v1.1, June 2025).
This article is general information, not legal advice. Check the current legislation, the NCC edition that applies to your project and your project specification before relying on it.